File #: 25-0316    Version: 1 Name:
Type: Contract Amendment Status: Agenda Ready
File created: 8/14/2025 In control: FPD Board of Commissioners
On agenda: 9/9/2025 Final action:
Title: PROPOSED CONTRACT AMENDMENT Department(s): Department of Planning and Development Vendor: Interface Engineering, Chicago, Illinois Request: Authorization for the Forest Preserves of Cook County (the "Forest Preserves") to increase contract Good(s) or Service(s): Professional Services to provide architectural and engineering design and construction administration services for a new heating and air conditioning system for the Forest Preserves' General Headquarters in River Forest. Original Contract Period: 12/15/2021 - 3/14/2025; 3/15/2025 - 3/14/2026 (Administrative Extension) Proposed Contract Period Extension: N/A Total Current Contract Amount Authority: $351,628.00 Original Approval: 12/14/2021, $184,846.00 Previous Increase(s): 3/25/2022, $17,450.00 (Administrative Increase); 4/5/2022, $55,215.00 (Board Approval); 2/7/2023, $74,989.00 (Board Approval); and 8/27/2025, $19,128.00 (Administrative Increase) This Increase Requested: $38,610.00 Estimated Fis...
Indexes: ADAM BIANCHI, General Superintendent
Related files: 23-0168, 23-0019, 21-0476, 22-0189
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
PROPOSED CONTRACT AMENDMENT

Department(s): Department of Planning and Development

Vendor: Interface Engineering, Chicago, Illinois

Request: Authorization for the Forest Preserves of Cook County (the "Forest Preserves") to increase contract

Good(s) or Service(s): Professional Services to provide architectural and engineering design and construction administration services for a new heating and air conditioning system for the Forest Preserves' General Headquarters in River Forest.

Original Contract Period: 12/15/2021 - 3/14/2025; 3/15/2025 - 3/14/2026 (Administrative Extension)

Proposed Contract Period Extension: N/A

Total Current Contract Amount Authority: $351,628.00

Original Approval: 12/14/2021, $184,846.00

Previous Increase(s): 3/25/2022, $17,450.00 (Administrative Increase); 4/5/2022, $55,215.00 (Board Approval); 2/7/2023, $74,989.00 (Board Approval); and 8/27/2025, $19,128.00 (Administrative Increase)

This Increase Requested: $38,610.00

Estimated Fiscal Impact: FY 2025 $38,610.00

Accounts: Professional Services 51009.520830, 51031.520830, 51033.520830, 51034.520830 and 51036.520830; and future Construction and Development accounts

Contract Number(s): #74000009962 issued under RFP #21-80-44

Concurrences: The Chief Financial Officer has approved this item. Final amendment is subject to legal review and approval.

The Vendor has met the Minority- and Women-Owned Business Enterprise Ordinance via direct participation.

District(s): 9

Summary: The original scope of services was for design, construction administration and commissioning of a new Very High Efficiency (VHE), all-electric heating and cooling (HVAC) system at the Forest Preserves' General Headquarters. Additional services are needed for the continuation of commissioning required by a ComEd grant for the VHE HVAC system following an unforeseen installation problem. Piping was installed incorrectly between equipment units that had already been tested and commi...