Title: PROPOSED BID RECOMMENDATION Department: Department of Planning and Development Request: Authorization for the Forest Preserves of Cook County (the "Forest Preserves") to enter into a construction contract with CPMH, primary place of business Chicago, Illinois, for installing concrete sidewalks, relocating sidewalks and modifying structures to meet ADA access requirements. Reason: Contract #74000008006 issued under Project #20-80-31 Camp Bullfrog Walkway and Access Improvement includes, but is not limited to, removing existing concrete and aggregate walkways, relocating and installing new walkways, and modifying existing wooden structures to make all ADA compliant at Camp Bullfrog. Work also includes installing new catch basins, storm sewers, asphalt paving and patching and other related work as specified in the plans and specifications. Bid Opening Date: 6/12/2020 Bid Results: 1. CPMH $244,650.36 2. Pan-Oceanic Engineering Co., Inc. $311,702.70 3. Path Construction Co., I...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent

title

PROPOSED BID RECOMMENDATION

 

Department:  Department of Planning and Development

 

Request: Authorization for the Forest Preserves of Cook County (the “Forest Preserves”) to enter into a construction contract with CPMH, primary place of business Chicago, Illinois, for installing concrete sidewalks, relocating sidewalks and modifying structures to meet ADA access requirements.

 

Reason: Contract #74000008006 issued under Project #20-80-31 Camp Bullfrog Walkway and Access Improvement includes, but is not limited to, removing existing concrete and aggregate walkways, relocating and installing new walkways, and modifying existing wooden structures to make all ADA compliant at Camp Bullfrog. Work also includes installing new catch basins, storm sewers, asphalt paving and patching and other related work as specified in the plans and specifications.

 

Bid Opening Date:  6/12/2020

 

Bid Results:

1.  CPMH                     $244,650.36

2.  Pan-Oceanic Engineering Co., Inc.                     $311,702.70

3.  Path Construction Co., Inc.                     $323,558.00

4.  Robe, Inc.                     $447,432.17

 

Estimated Fiscal Impact: $244,650.36

 

Contract Period:  One hundred and twenty (120) days from notice to proceed

 

Account Name/Number: Land Improvements 51025.560019, 51027.560019, 51028.560019, 51051.560019, 51056.560019, 51057.560019, and 51058.560019; Future Construction and Development Accounts

 

District: 17

 

Concurrence(s):

The Chief Financial Officer and Chief Attorney have approved this item.

 

The Vendor has met the Minority- and Women-Owned Business Enterprise Ordinance via direct participation.