title
PROPOSED CONTRACT AMENDMENT
Department(s): Planning and Development
Vendor: Chicago Commercial Construction Inc., Chicago, Illinois
Request: Authorization for the Forest Preserve District of Cook County to extend, contract
Good(s) or Service(s): Deer Grove and Tinley Creek Outdoor Interpretation
Original Contract Period: Two hundred and forty (240) days from Notice to Proceed (2/20/2015 - 2/15/2016); sixty (60) day administrative extension (2/16/2016 - 4/16/2016); two hundred and fifty-eight (258) day extension (4/17/2016 - 12/31/2016): two hundred and ninety-one (291) day extension (1/17/2017 - 10/18/2017)
Proposed Contract Period Extension: Two hundred thirty-nine (239) day extension retroactively from 10/19/2017 - 6/15/2018
Total Current Contract Amount Authority: $836,289.65
Original Approval: 1/20/2015, $836,289.65
Previous Increase(s): N/A
This Increase Requested: N/A
Estimated Fiscal Impact: None
Accounts: Site Improvement Accounts, 51025.560060, 51054.560060 and 51055.560060
Contract Number(s): 13-80-02-05C4-R
Concurrences:
The Chief Financial Officer and Chief Attorney have approved this item.
The Vendor has met the Minority and Women Business Enterprise Ordinance Provisions.
District(s): 6 and 14
Summary: Work is substantially complete. A contract extension is required to provide additional time for punch list work and project closeout. A few punch list items are weather dependent, requiring extension until warmer weather.
end