title
PROPOSED CONTRACT AMENDMENT
Department(s): Planning and Development
Vendor: Path Construction Company, Arlington Heights, Illinois
Request: Authorization for the Forest Preserve District of Cook County to increase a previously awarded contract
Good(s) or Service(s): Construction services for improvements to various buildings at the Central Garage and Warehouse Complex
Original Contract Period: (10/26/2015 - 4/23/2016), Administrative Extension, (4/24/2016 - 6/23/2016), Board Approved Extension (6/24/2016 - 3/21/2017)
Proposed Contract Period Extension: N/A
Total Current Contract Amount Authority: $1,026,100.00
Original Approval: 4/14/2015 $1,026,100.00
Previous Increase(s): N/A
This Increase Requested: $112,040.75
Estimated Fiscal Impact: $112,040.75
Accounts: Building Accounts 55-6710, 56-6710, 09-6710, 25-6710 and 26-6710
Contract Number(s): 13-80-01-G5R2
Concurrences:
The Chief Financial Officer and Chief Attorney have approved this item.
The Vendor has met the Minority and Women Business Enterprise Ordinance Provisions.
District(s): 1
Summary: Additional funds are required to perform the work. This work is required for code compliance that was determined during the permitting process with Cook County Building and Zoning as well as the Village of Maywood. This project includes making improvements for ADA accessibility, life safety issues as well as office and restroom functionality.