title
PROPOSED CONTRACT AMENDMENT
Department(s): Planning & Development
Vendor: Mack Construction Corporation, Tinley Park, Illinois
Request: Authorization for the Forest Preserve District of Cook County to extend a previously executed contract
Good(s) or Service(s): Construction services for the renovation of Dan Ryan Woods Visitor Center
Original Contract Period: 10/17/2014 - 8/13/2015, Administrative Extension (8/14/2015 - 10/12/2015), Board approved extension on 10/6/2015 (10/13/2015 - 4/9/2016)
Proposed Contract Period Extension: One hundred and eighty (180) calendar day extension (4/10/2016 - 10/7/2016)
Total Current Contract Amount Authority: $558,800.00
Original Approval: 7/22/2014, $558,800.00
Previous Increase(s): N/A
This Increase Requested: N/A
Estimated Fiscal Impact: N/A
Accounts: Building Accounts 25-6710, 26-6710, 52-6710, 54-6710, 55-6710, 56-6710 and 09-6710
Contract Number(s): 13-80-01-G5R3
Concurrences:
The Chief Financial Officer and Chief Attorney have approved this item.
The Vendor has met the Minority and Women Business Enterprise Ordinance Provisions.
District(s): 4
Summary: An extension is required to perform closeout activities. This request is for time only. All work has been completed and the Preserves is occupying the building.
end