File #: 15-0563    Version: 1 Name: Century Contractors Inc., Bedford Park, Illinois
Type: Contract Amendment Status: Approved
File created: 9/17/2015 In control: FPD Board of Commissioners
On agenda: 10/6/2015 Final action: 10/6/2015
Title: PROPOSED CONTRACT AMENDMENT Department(s): Planning and Development Vendor: Century Contractors Inc., Bedford Park, Illinois Request: Authorization for the Forest Preserve District of Cook County to extend contract Good(s) or Service(s): Construction services for various trail improvements at thirteen (13) locations Districtwide Original Contract Period: Two hundred ten (210) days from the issuance of the Notice to Proceed. 4/4/2014 through 11/4/2014 Administrative Extension: N/A Previous Board Extension: Three hundred sixty five (365) days Extension beginning 11/5/2014 -11/4/2015 Proposed Contract Period Extension: Three hundred sixty five (365) day extension from 11/5/2015 - 11/4/2016 Total Current Contract Amount Authority: $536,595.00 Original Approval: 3/11/2014, $536,595.00 Previous Increase(s): N/A This Increase Requested: N/A Estimated Fiscal Impact: None Accounts: Recreation (Landscape Improvements) Accounts 25-6760,...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent

title

PROPOSED CONTRACT AMENDMENT

 

Department(s):  Planning and Development

 

Vendor:  Century Contractors Inc., Bedford Park, Illinois

 

Request:  Authorization for the Forest Preserve District of Cook County to extend  contract 

 

Good(s) or Service(s):  Construction services for various trail improvements at thirteen (13) locations Districtwide

 

Original Contract Period:  Two hundred ten (210) days from the issuance of the Notice to Proceed. 4/4/2014 through 11/4/2014

Administrative Extension:  N/A

 

Previous Board Extension:  Three hundred sixty five (365) days Extension beginning 11/5/2014 -11/4/2015

 

Proposed Contract Period Extension:  Three hundred sixty five (365) day extension from 11/5/2015 - 11/4/2016

 

Total Current Contract Amount Authority:   $536,595.00

 

Original Approval:  3/11/2014, $536,595.00

 

Previous Increase(s):  N/A

 

This Increase Requested:  N/A

 

Estimated Fiscal Impact:  None

 

Accounts:  Recreation (Landscape Improvements) Accounts 25-6760, 51-6760, 52-6760, 54-6760 and 55-6760

 

Contract Number(s):  13-80-02-12C1

 

Concurrences:

The Chief Financial Officer and Chief Attorney have approved this item.

 

The Vendor has met the Minority and Women Business Enterprise Ordinance Provisions.

 

District(s):  Districtwide

 

Summary:  A contract extension is required due to contractor capacity constraints, delay caused by weather and material supply issues.