File #: 15-0420    Version: 1 Name:
Type: Contract Amendment Status: Approved
File created: 7/1/2015 In control: FPD Board of Commissioners
On agenda: 7/21/2015 Final action: 7/21/2015
Title: PROPOSED CONTRACT AMENDMENT Department(s): Planning and Development Vendor: Domokur Architects, Lombard Il Request: Authorization for the Forest Preserve District of Cook County to increase a previously executed task order for architectural and engineering services contract Good(s) or Service(s): Professional Services Original Contract Period: Thirty-two (32) months from the issuance of the Notice To Proceed, (4/30/13 - 12/31/15) Proposed Contract Period Extension: Three (3) months (1/1/16-3/31/16 Total Current Contract Amount Authority: $2,017,721.00 Original Approval: 04/16/13, $1,872,755.00 Previous Increase(s): Administrative Increase 06/02/14, $144,966.00 This Increase Requested: $87,773.34 Estimated Fiscal Impact: $87,773.34 Accounts: Camp Accounts: 25-6740, 26-6740, 51-6740, 52-6740, 54-6740, and 55-6740 Contract Number(s): Task Order #13-80-03-001-D Concurrences: The Chief Financial Officer and Chief Attorney ha...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent
title
PROPOSED CONTRACT AMENDMENT

Department(s): Planning and Development

Vendor: Domokur Architects, Lombard Il

Request: Authorization for the Forest Preserve District of Cook County to increase a previously executed task order for architectural and engineering services contract

Good(s) or Service(s): Professional Services

Original Contract Period: Thirty-two (32) months from the issuance of the Notice To Proceed, (4/30/13 - 12/31/15)

Proposed Contract Period Extension: Three (3) months (1/1/16-3/31/16

Total Current Contract Amount Authority: $2,017,721.00

Original Approval: 04/16/13, $1,872,755.00

Previous Increase(s): Administrative Increase 06/02/14, $144,966.00

This Increase Requested: $87,773.34

Estimated Fiscal Impact: $87,773.34

Accounts: Camp Accounts: 25-6740, 26-6740, 51-6740, 52-6740, 54-6740, and 55-6740

Contract Number(s): Task Order #13-80-03-001-D

Concurrences:
The Chief Financial Officer and Chief Attorney have approved this item.

The Vendor has met the Minority and Women Business Enterprise Ordinance Provisions.

Summary: Contract (Task Order) #13-80-03-001-D is for architectural and engineering design services for the District's Camp capital improvement program. At this time additional services and a three (3) month time extension are needed to better accommodate the programs and services now being proposed for the Camp Sullivan Barn and Maple Lake Boathouse Dock. These services are required to better accommodate the activities identified by Preserve staff and the camp manager, including expansion of doors and changes to cabinets, countertops and plumbing fixtures at the barn and addition of floating docks and ramps at the boathouse. This contract was originally approved at the April 16, 2013 Board Meeting and revised administratively on June 2, 2014. The original project scope for this project included design and construction administration services for the entire C...

Click here for full text