Title: PROPOSED CONTRACT AMENDMENT Department(s): Planning and Development Vendor: Burling Builders, Inc., Chicago, Illinois Request: Authorization for the Forest Preserve District of Cook County to increase and extend a previously executed construction contract Good(s) or Service(s): New Metal Buildings or Additions at the Central Maintenance Garage Compound in Maywood, the Thorn Creek Maintenance Division in Lansing, and Palos Trails & Grounds in Willow Springs Original Contract Period: 7/10/2014 - 7/6/2015 Proposed Contract Period Extension: 7/7/2015 - 9/6/2015 Total Current Contract Amount Authority: $3,993,343.00 Original Approval: 4/8/2014, $3,993,343.00 Previous Increase(s): None This Increase Requested: $755,380.73 Estimated Fiscal Impact: $755,380.73 Accounts: Building Accounts: 25-6710, 26-6710, 51-6710, 52-6710, 54-6710 & 55-6710 Contract Number(s): Contract #13-80-01-G3R1 & G3R2 Concurrences: The Chief Financial Off...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent
title
PROPOSED CONTRACT AMENDMENT
 
Department(s):  Planning and Development  
 
Vendor:  Burling Builders, Inc., Chicago, Illinois
 
Request:  Authorization for the Forest Preserve District of Cook County to increase and extend a previously executed construction  contract  
 
Good(s) or Service(s):  New Metal Buildings or Additions at the Central Maintenance Garage Compound in Maywood, the Thorn Creek Maintenance Division in Lansing, and Palos Trails & Grounds in Willow Springs
 
Original Contract Period:  7/10/2014 - 7/6/2015  
 
Proposed Contract Period Extension:  7/7/2015 - 9/6/2015  
 
Total Current Contract Amount Authority:   $3,993,343.00
 
Original Approval:  4/8/2014, $3,993,343.00
 
Previous Increase(s):  None
 
This Increase Requested:  $755,380.73
 
Estimated Fiscal Impact:  $755,380.73
 
Accounts:  Building Accounts: 25-6710, 26-6710, 51-6710, 52-6710, 54-6710 & 55-6710
 
Contract Number(s):  Contract #13-80-01-G3R1 & G3R2
 
Concurrences:
The Chief Financial Officer and Chief Attorney have approved this item.
 
The Vendor has met the Minority and Women Business Enterprise Ordinance Provisions.
 
Summary:  The proposed contract increase is due to a number of items that require additional work necessary to complete the project.  Reasons for the increase include unforeseen conditions encountered during construction (i.e. unforeseen existing underground concrete obstructions) and permit code related changes required by County and local jurisdictions (i.e. revising underground & piping, interior electrical, plumbing and fire alarm equipment), and user improvements (i.e. LED lighting, upgrading existing offices, feeders for fueling stations and fire alarm improvements). The final contract completion date allows for sixty (60) additional days for closeout.
The Preserves is currently seeking approval of a $755,380.73 addition to increase the total contract amount to $4,748,723.73.   