File #: 15-0197    Version: 1 Name: All Bry Construction, Burr Ridge, IL
Type: Bid Recommendation Status: Approved
File created: 2/17/2015 In control: Finance Committee
On agenda: 3/10/2015 Final action: 3/10/2015
Title: PROPOSED BID RECOMMENDATION Presented by: ARNOLD RANDALL, GENERAL SUPERINTENDENT Department: Planning and Development Request: Authorization for the Forest Preserve District of Cook County (the "Preserves") to enter into a contract with All Bry Construction, Burr Ridge, Illinois, for the renovation of an existing barn at Camp Sullivan in Oak Forest, Illinois, as an indoor activity and gathering space. Reason: Contract 13-80-03-009-C Camp Sullivan Barn Phase 3. The project includes the renovation and remodeling of the Camp Sullivan barn as an indoor activity space for the Camp Sullivan campgrounds. The project also includes site work, landscaping, structural, exterior finishes, new interior spaces, new restrooms, interior architectural finishes, interior wheelchair lift, interior climbing wall, and MEP&FP and other related work as specified in the plans & specifications. Bid Opening Date: 2/11/2015 Bid Results: Firm Base Bid Alt. Bid Items G1a and G2a**...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent
title
PROPOSED BID RECOMMENDATION

Presented by: ARNOLD RANDALL, GENERAL SUPERINTENDENT

Department: Planning and Development

Request: Authorization for the Forest Preserve District of Cook County (the "Preserves") to enter into a contract with All Bry Construction, Burr Ridge, Illinois, for the renovation of an existing barn at Camp Sullivan in Oak Forest, Illinois, as an indoor activity and gathering space.

Reason: Contract 13-80-03-009-C Camp Sullivan Barn Phase 3. The project includes the renovation and remodeling of the Camp Sullivan barn as an indoor activity space for the Camp Sullivan campgrounds. The project also includes site work, landscaping, structural, exterior finishes, new interior spaces, new restrooms, interior architectural finishes, interior wheelchair lift, interior climbing wall, and MEP&FP and other related work as specified in the plans & specifications.

Bid Opening Date: 2/11/2015

Bid Results:
Firm Base Bid Alt. Bid Items G1a and G2a** Total Bid
1. All Bry Construction $2,407,000* $39,000 $2,446,000
2. Path Construction $2,427,200 $55,900 $2,483,100
3. Burling Builders, Inc $2,474,000 $84,300 $2,558,300
4. Cornerstone Contracting, Inc $2,531,000 $160,000 $2,691,000
5. Wight Construction $2,911,632 $10,000 $2,921,632
6. F.H. Paschen $2,998,000 $62,326 $3,060,326
7. Oakley Construction $3,094,629 $18,000 $3,112,629

* All Bry Construction's bid was read into the record as $2,397,000.00, but after further examination, they made a mathematical error in their calculations. Their actual bid is $2,407,000.00.

** Alternate Bid Items G1a and G2a - Structural columns and foundations could not be tested at the time of design without impacting the existing structure. If structural testing during construction shows the columns and foundations are inadequate, these alternate items will be completed as part of the construction.

Estimated Fiscal Impact: $2,446,000.0...