File #: 15-0192    Version: 1 Name: CXT, Inc. an L.B. Foster Company, Spokane, WA
Type: Contract Amendment Status: Approved
File created: 2/13/2015 In control: FPD Board of Commissioners
On agenda: 3/10/2015 Final action: 3/10/2015
Title: PROPOSED CONTRACT AMENDMENT Department(s): Planning and Development Vendor: CXT, Inc. an L.B. Foster Company, Spokane, Washington Request: Authorization for the Forest Preserve District of Cook County to extend contract Good(s) or Service(s): Purchase of four (4) prefabricated toilet buildings Original Contract Period: 1/29/2014 - 1/28/2015 Proposed Contract Period Extension: Three (3) Month Extension 3/30/2015-6/30/2015 Total Current Contract Amount Authority: $222,568.00 Original Approval: Item #14, 10/1/2013, $222,568.00 Previous Increase(s): N/A Previous Extension: Sixty (60) days 1/29/2015 - 3/29/2015 This Increase Requested: N/A Estimated Fiscal Impact: None Accounts: Building Accounts 51-6710 and 52-6710 Contract Number(s): 13-80-46B Concurrences: The Chief Financial Officer and Chief Attorney have approved this item. Summary: A contract extension is required because the corresponding site work...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent
title
PROPOSED CONTRACT AMENDMENT
 
Department(s):  Planning and Development  
 
Vendor:  CXT, Inc. an L.B. Foster Company, Spokane, Washington  
 
Request:  Authorization for the Forest Preserve District of Cook County to extend  contract  
 
Good(s) or Service(s):  Purchase of four (4) prefabricated toilet buildings   
 
Original Contract Period:  1/29/2014 - 1/28/2015
 
Proposed Contract Period Extension:  Three (3) Month Extension 3/30/2015-6/30/2015
 
Total Current Contract Amount Authority:   $222,568.00
 
Original Approval:  Item #14, 10/1/2013, $222,568.00
 
Previous Increase(s):  N/A
 
Previous Extension: Sixty (60) days 1/29/2015 - 3/29/2015  
 
This Increase Requested:  N/A
 
Estimated Fiscal Impact:  None
 
Accounts:  Building Accounts 51-6710 and 52-6710
 
Contract Number(s):  13-80-46B
 
Concurrences:
The Chief Financial Officer and Chief Attorney have approved this item.
 
Summary:  A contract extension is required because the corresponding site work necessary to be completed for the installation of these units has been delayed.
 
Contract 13-80-46B includes the fabrication and delivery of four (4) prefabricated flush toilet buildings at Barrington Road Pond (District 15), Harms Woods-North (District 14), Schiller Woods-West (District 9) and North Creek Meadow (District 6).  
 
These units are being purchased from a national prefabricated toilet manufacturer through National Joint Purchasing Alliance Contract #022113-CXT pursuant to Section 1-8-2(AA) of the District's Code of Ordinances.
 
The project specific goals regarding the MBE/WBE participation for this project was zero (0) because the product is a sole manufacturer by one vendor.
end