File #: 14-1001    Version: 1 Name: Chicago Commercial Construction, Chicago, Illinois new picnic shelters and site improvements at Rubio Woods and new program shelter and site improvements at the Chicago Portage Site
Type: Bid Recommendation Status: Approved
File created: 11/21/2014 In control: Finance Committee
On agenda: 12/16/2014 Final action: 12/16/2014
Title: PROPOSED BID RECOMMENDATION Presented by: ARNOLD RANDALL, GENERAL SUPERINTENDENT Department: Planning and Development Request: Authorization for the Forest Preserve District of Cook County (the "Forest Preserves") to enter into a contract with Chicago Commercial Construction, Chicago, Illinois, for new picnic shelters and site improvements at Rubio Woods and new program shelter and site improvements at the Chicago Portage Site Reason: Contract 13-80-02-08C1 For new Picnic Shelters at Rubio Woods and program shelter at the Chicago Portage Site. The work includes, but is not limited to, structure demolition, trail removal, clearing, concrete paving, asphalt paving, landscaping, new picnic and program shelters, and other related work as specified in the plans & specifications. Bid Opening Date: 11/7/2014 Bid Results: Firm Bid Amount 1. Chicago Commercial Construction $848,802.16* 2. John Burns Construction $916,391.38 3. FH Paschen $944,47...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent
title
PROPOSED BID RECOMMENDATION
 
Presented by: ARNOLD RANDALL, GENERAL SUPERINTENDENT
 
Department:  Planning and Development
 
Request:  Authorization for the Forest Preserve District of Cook County (the "Forest Preserves") to enter into a contract with Chicago Commercial Construction, Chicago, Illinois, for new picnic shelters and site improvements at Rubio Woods and new program shelter and site improvements at the Chicago Portage Site
 
Reason:   Contract 13-80-02-08C1 For new Picnic Shelters at Rubio Woods and program shelter at the Chicago Portage Site.  The work includes, but is not limited to, structure demolition, trail removal, clearing, concrete paving, asphalt paving, landscaping, new picnic and program shelters, and other related work as specified in the plans & specifications.
 
Bid Opening Date:  11/7/2014
 
Bid Results:
Firm                                                Bid Amount
1. Chicago Commercial Construction                        $848,802.16*
2. John Burns Construction                              $916,391.38
3. FH Paschen                                          $944,478.96
4. Simpson Construction                              $1,017,007.49
5. Paul Borg                                          $1,081,880.94
6. Schaefges Brothers, Inc                              $1,180,655.60
 
*Chicago Commercial Construction's bid was read into the record as $903,786.69, but after further examination, they made a mathematical error in their calculations. Their actual bid is $848,802.16.
 
Estimated Fiscal Impact: $848,802.16
 
Contract Period:  209 days from notice to proceed
 
Account Name/Number:  Recreation Landscape Accounts 25-6760, 51-6760, 52-6760 &54-6760
 
District: 6&16   
 
Concurrence(s):
The vendor has met the Minority and Women Business Enterprise Ordinance provision.
The Chief Attorney and Chief Financial Officer have approved this item.