File #: 14-0343    Version: 1 Name: with Path Construction Company Inc., Arlington Heights, Illinois
Type: Bid Recommendation Status: Approved
File created: 7/1/2014 In control: Finance Committee
On agenda: 7/22/2014 Final action: 7/22/2014
Title: PROPOSED BID RECOMMENDATION Presented by: ARNOLD L. RANDALL, General Superintendent Department: Planning and Development Request: requesting authorization for the Forest Preserves of Cook County (the "Preserves") to enter into a contract with Path Construction Company Inc., Arlington Heights, Illinois, for construction of Phase 2 of Camp Sullivan near Oak Forest, Illinois. Reason: Contract 13-80-03-007-C is for the Camp Sullivan Family Development Phase 2. The work includes, but is not limited to, the construction of a new camp ground with drive-in and walk-in camp sites, two small cabins, toilet/showers, landscaping, development of trails/paths, site furnishings, utilities, site development, parking, signage and other related work as specified in the plans and specifications. Bid Opening Date: 6/18/2014 Bid Results: Firm Base Bid Recommended Deduct Alternate Bid 1. Path Construction Company Inc., $2,265,200.00 $2,247,200.00 2. Burling Buil...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent
title
PROPOSED BID RECOMMENDATION
 
Presented by: ARNOLD L. RANDALL, General Superintendent
 
Department:  Planning and Development
 
Request:  requesting authorization for the Forest Preserves of Cook County (the "Preserves") to enter into a contract with Path Construction Company Inc., Arlington Heights, Illinois, for construction of Phase 2 of Camp Sullivan near Oak Forest, Illinois.   
 
Reason:   Contract 13-80-03-007-C is for the Camp Sullivan Family Development Phase 2.  The work includes, but is not limited to, the construction of a new camp ground with drive-in and walk-in camp sites, two small cabins, toilet/showers,  landscaping, development of trails/paths, site furnishings, utilities, site development, parking, signage and other related work as specified in the plans and specifications.
 
Bid Opening Date:  6/18/2014  
 
Bid Results:
Firm                              Base Bid            Recommended Deduct Alternate Bid
1.  Path Construction Company Inc.,   $2,265,200.00                  $2,247,200.00
2.  Burling Builders, Inc.,            $2,595,000.00                   $2,572,000.00
 
Base bid amounts included line item costs for standing seam metal roofing for all structures.  The bid recommendation is to award the contract with deduct alternate #1-Furnish and install Asphalt Shingles in lieu of Standing Seam Metal Roof Panels at 2 toilet/shower Buildings, and small cabins.
 
Estimated Fiscal Impact: $2,247,200.00
 
Contract Period:  Three hundred and fifty (350) days from notice to proceed.
 
Account Name/Number:  Camp,  25-6730, 51-6730, 52-6730, 54-6730
 
District: 6  
 
Concurrence(s):
The vendor has met the Minority and Women Business Enterprise Ordinance provision.
The Comptroller and Chief Attorney have approved this item.