File #: 14-0335    Version: 1 Name: All-Bry Construction Company, Burr Ridge, Illinois
Type: Bid Recommendation Status: Approved
File created: 6/30/2014 In control: Finance Committee
On agenda: 7/22/2014 Final action: 7/22/2014
Title: PROPOSED BID RECOMMENDATION Presented by: ARNOLD L. RANDALL, General Superintendent Department: Planning and Development Request: requesting authorization for the Forest Preserves of Cook County (the "Preserves") to enter into a contract with All-Bry Construction Company, Burr Ridge, Illinois, for building and site improvements at the Swallow Cliff Stairs in Palos Park. Reason: Contract 13-80-01 G7R2 is for Warming Shelter Building and Site Improvements at Swallow Cliff Woods North. The proposed project is the development of a new warming shelter including, but not limited to, construction of a multi-use space, a concession area and flush toilets. The project also includes development of a patio, paths, utilities, landscaping, improvements to the overlook area located at the top of the hill and other related work as specified in the plans & specifications. Bid Opening Date: 6/4/2014 Bid Results: Firm Base Bid 1. All-Bry Construction Company ...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent
title
PROPOSED BID RECOMMENDATION

Presented by: ARNOLD L. RANDALL, General Superintendent

Department: Planning and Development

Request: requesting authorization for the Forest Preserves of Cook County (the "Preserves") to enter into a contract with All-Bry Construction Company, Burr Ridge, Illinois, for building and site improvements at the Swallow Cliff Stairs in Palos Park.

Reason: Contract 13-80-01 G7R2 is for Warming Shelter Building and Site Improvements at Swallow Cliff Woods North. The proposed project is the development of a new warming shelter including, but not limited to, construction of a multi-use space, a concession area and flush toilets. The project also includes development of a patio, paths, utilities, landscaping, improvements to the overlook area located at the top of the hill and other related work as specified in the plans & specifications.

Bid Opening Date: 6/4/2014

Bid Results:
Firm Base Bid
1. All-Bry Construction Company $1,564,000.00
2. Path Construction Co. Inc $1,667,600.00
3. Chicago Commercial Construction $1,682,323.53*
4. Plata Corporation $1,800,989.00
5. The Lombard Company $1,805,000.00
6. Friedler Construction $1,832,701.00**
7. Brown & Momem Inc. $2,431,500.00


* Chicago Commercial Construction's bid was read into the record as $1,682,323.50, but after further examination, Chicago Commercial Construction made a mathematical error in their calculations. Their actual bid is $1,682,323.53.

** Friedler Construction Co.'s bid was read into the record as $1,820,800.00, but after further examination, Friedler Construction Co. made a mathematical error in their calculations. Their actual bid is $1,832,701.00.

Estimated Fiscal Impact: $1,564,000.00

Contract Period: Three Hundred (300) days from notice to proceed

Account Name/Number: Building Accounts 25-6710, 52-6710 and 54-6710 & Grant Account 10-6710

District: 17

Concurrence(s...