Title: PROPOSED CONTRACT AMENDMENT Department(s): Planning and Development Vendor: AGAE Contractors, Inc., Chicago, Illinois Request: Authorization for the Forest Preserve District of Cook County to extend and increase a previously amended Job Order Contract (JOC) contract Good(s) or Service(s): Construction services for life safety, ADA and locker room improvements at the Preserves' Skokie Resource Management Headquarters, Glen Grove Equestrian Center and North Branch Maintenance Headquarters. Original Contract Period: 3/27/2014 - 3/18/2015, Administrative extension (3/19/2015 - 5/18/2015); Board approved extensions (5/19/2015 - 5/18/2016) and (5/19/2016 - 11/15/2016) Proposed Contract Period Extension: Ninety (90) days (11/16/2016 - 2/14/2017) Total Current Contract Amount Authority: $352,075.92 Original Approval: 12/18/2013, $303,377.00 Previous Increase(s): 10/6/2015, $48,698.92 This Increase Requested: $40,961.75 Estimated Fiscal Impact: $40,961.75 A...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent

title

PROPOSED CONTRACT AMENDMENT

 

Department(s):  Planning and Development 

 

Vendor:  AGAE Contractors, Inc., Chicago, Illinois 

 

Request:  Authorization for the Forest Preserve District of Cook County to extend and increase a previously amended Job Order Contract (JOC)  contract 

 

Good(s) or Service(s):  Construction services for life safety, ADA and locker room improvements at the Preserves’ Skokie Resource Management Headquarters, Glen Grove Equestrian Center and North Branch Maintenance Headquarters. 

 

Original Contract Period:  3/27/2014 - 3/18/2015, Administrative extension (3/19/2015 - 5/18/2015); Board approved extensions (5/19/2015 - 5/18/2016) and (5/19/2016 - 11/15/2016) 

 

Proposed Contract Period Extension:  Ninety (90) days (11/16/2016 - 2/14/2017) 

 

Total Current Contract Amount Authority:   $352,075.92

 

Original Approval:  12/18/2013, $303,377.00

 

Previous Increase(s):  10/6/2015, $48,698.92

 

This Increase Requested:  $40,961.75

 

Estimated Fiscal Impact:  $40,961.75

 

Accounts:  Building Accounts 25-6710, 26-6710, 52-6710, 54-6710, 55-6710, 56-6710 and 09-6710.

 

Contract Number(s):  13-80-01-G2R1

 

Concurrences:

The Chief Financial Officer and Chief Attorney have approved this item.

 

The Vendor has met the Minority and Women Business Enterprise Ordinance Provisions.

 

District(s):  6 and 11

 

Summary: The work is substantially complete except for fire alarm system installations. Design and permitting resulted in a significant increase in the number of fire alarm devices. Additional funding is required to furnish and install fire alarm systems as required by local Fire Prevention Districts.  Completion of close-out activities also remains.   end