title
PROPOSED PREVIOUSLY APPROVED ITEM AMENDMENT
Department: Department of Planning and Development
Request: Authorization to amend the previous board approval to update fiscal impact and summary. On July 1, 2025, the Board of Commissioners previously approved the award of a contract for Phase III construction engineering services but the contract was never executed due to delays in bidding of the project by the Illinois Department of Transportation ("IDOT"). The vendor has submitted an updated cost proposal in anticipation of an IDOT construction bid posting in the near future. Forest Preserve staff are also seeking authorization for a modest contingency in the event of further prolonged delay in construction bidding.
Item Number: 25-0033
Fiscal Impact: Previous value of $690,563.00 increased by $162,724.60 ($85,153 plus 10% contingency $77,571.60) to a total of $853,287.60
Original Text of Item:
PROPOSED CONTRACT
Department(s): Department of Planning and Development
Vendor: Bowman Consulting Group Ltd., Lisle, Illinois
Request: Authorization for the Forest Preserves of Cook County (the "Forest Preserves") to enter into and execute
Good(s) or Service(s): Phase III engineering services for construction oversight relating to construction of a bridge over the Union Pacific Railroad connecting the Des Plaines River Trail from Golf Road to Central Road
Contract Value: $690,563.00 $853,287.60
Contract Period: 9/1/2025 - 12/1/2027
Estimated Fiscal Impact: FY2025 $69,056.30, FY2026 $552,450.40, FY2027 $69,056.30 subject to grant reimbursement of 80% ($552,450.40) or up to $664,980.00 if supplemental GCP funding is approved. FY2026 $85,328.70, FY27 $725,293.95, FY28 $42,664.35). Subject to grant reimbursements ($324,900 ICC Grade Crossing Protection funds and $360,652.80 TAP-L funds with local share of $90,163.20 excluding contingency).
Accounts: Professional Services 51009.520830, 51010.520830, 51029.520830, 51033.520830, 51034.520830, 51036.5208...