title
PROPOSED CONTRACT AMENDMENT
 
Department(s):  Planning and Development
 
Vendor:  URS Corporation Inc, Chicago, Illinois
 
Request:  Authorization for the Forest Preserve District of Cook County to extend contract  
 
Good(s) or Service(s):  Thorn Creek Bicycle Trail Extension Phase III engineering
 
Original Contract Period:  Three hundred sixty five (365) days from Notice to Proceed 6/2/2014 - 6/2/2015
Administrative Extension:  N/A
 
Proposed Contract Period Extension:  Three hundred sixty five (365) day extension retroactive from 6/03/2015 - 6/2/2016
 
Total Current Contract Amount Authority:   $454,781.62
 
Original Approval:  2/4/2013, $454,781.62
 
Previous Increase(s):  N/A 
 
This Increase Requested:  N/A 
 
Estimated Fiscal Impact:  None 
 
Accounts:  Consulting Account, 51-6740 and Grant Account, 10-6240
 
Contract Number(s):  06-80-03
 
Concurrences:
The Chief Financial Officer and Chief Attorney have approved this item. 
 
The Vendor has met the Minority and Women Business Enterprise Ordinance Provisions.
 
District(s): 5 and 6
 
Summary:  This contract extension is required to oversee the related Stage I and Stage II construction contracts.  Stage I construction, now substantially complete and open to the public, was delayed due to weather.  Stage II construction, which added trail mileage and the construction of a railroad underpass, was delayed due to extended negotiations and approvals with the railroad.
end