title
PROPOSED CONTRACT AMENDMENT
 
Department(s):  Planning and Development
 
Vendor:  Path Construction Company, Arlington Heights, Illinois
 
Request:  Authorization for the Forest Preserve District of Cook County to extend a previously executed  contract  
 
Good(s) or Service(s):  Constructions services for improvements to various buildings at the Central Garage and Warehouse Complex
 
Original Contract Period:  10/26/2015 - 4/23/2016, Administrative Extension 4/24/2016 - 6/23/2016; Board approved extension 6/24/2016 - 3/21/2017; Board approved extension 3/22/2017 - 7/20/2017
 
Proposed Contract Period Extension:  7/21/2017, retroactive - 12/31/2017
 
Total Current Contract Amount Authority:   $1,240,471.02 
 
Original Approval:  4/14/2015, $1,026,100.00
 
Previous Increase(s):  9/13/2016, $112,040.75; Administrative Increase $102,330.27
 
This Increase Requested:  N/A 
 
Estimated Fiscal Impact:  N/A
 
Accounts:  N/A 
 
Contract Number(s):  13-80-01-G5R2
 
Concurrences:
The Chief Financial Officer and Chief Attorney have approved this item. 
 
The Vendor has met the Minority and Women Business Enterprise Ordinance Provisions.
 
District(s):  1
 
Summary:  This amendment is to extend time only. The project is substantially complete, however, additional time is required for electrical work and close-out activities. 
end