File #: 21-0319    Version: 1 Name:
Type: Bid Recommendation Status: Approved
File created: 6/7/2021 In control: Finance Committee
On agenda: 7/27/2021 Final action: 7/27/2021
Title: PROPOSED BID RECOMMENDATION Department: Department of Planning and Development Request: Authorization for the Forest Preserves of Cook County to enter into a construction contract with Fabex Technologies LLC, primary place of business Chicago, Illinois, for Masonry Repairs at Salt Creek Resource Management located near Western Springs. Reason: Contract #74000009402 issued under Project #21-80-14 Masonry Repairs at Salt Creek Resource Management. The work addresses repairs to three (3) existing buildings. The work includes, but is not limited to, masonry repairs, painting, sealant replacement, miscellaneous carpentry repairs and other related work as specified in the plans and specifications. Bid Opening Date: 6/16/2021 Bid Results: Bidder Bid Amount 1. Fabex Technologies, LLC $176,460.00 2. Berglund Construction $200,000.00 3. Bulley & Andrews Masonry Restoration, LLC $243,105.00 Estimated Fiscal Impact: $176,460.00 Contract Period: Two hundred ten (210) days fro...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent
Attachments: 1. MBE WBE Commitment Report July 2021

title

PROPOSED BID RECOMMENDATION

 

Department:  Department of Planning and Development

 

Request:  Authorization for the Forest Preserves of Cook County to enter into a construction contract with Fabex Technologies LLC, primary place of business Chicago, Illinois, for Masonry Repairs at Salt Creek Resource Management located near Western Springs.

 

Reason:   Contract #74000009402 issued under Project #21-80-14 Masonry Repairs at Salt Creek Resource Management. The work addresses repairs to three (3) existing buildings. The work includes, but is not limited to, masonry repairs, painting, sealant replacement, miscellaneous carpentry repairs and other related work as specified in the plans and specifications.

 

Bid Opening Date:  6/16/2021 

 

Bid Results:

                     Bidder                     Bid Amount

1.  Fabex Technologies, LLC                     $176,460.00

2.  Berglund Construction                     $200,000.00

3.  Bulley & Andrews Masonry Restoration, LLC                     $243,105.00

 

Estimated Fiscal Impact: $176,460.00

 

Contract Period:  Two hundred ten (210) days from issuance of notice to proceed

 

Account Name/Number:   Property Maintenance & Operations 51025.560105, 51028.560105, 51030.560105, 51051.560105, 51057.560105 and 51058.560105

 

District: 17

 

Concurrence(s):

The Chief Financial Officer and Chief Attorney have approved this item.

 

The vendor has met the Minority- and Women-owned Business Enterprise Ordinance provisions via direct participation.