title
PROPOSED CONTRACT AMENDMENT
 
Department(s):  Planning and Development
 
Vendor:  Cornerstone Contracting, Inc., Elk Grove Village, Illinois  
 
Request:  Authorization for the Forest Preserve District of Cook County to extend,  contract  
 
Good(s) or Service(s):  Camp Bullfrog/Maple Lake Development
 
Original Contract Period:  Three hundred fifty (350) days from Notice to Proceed 7/29/2014 - 7/14/2015
 
Administrative Extension:  Sixty (60) days extension granted by the Purchasing Agent 7/15/2015 - 9/13/2015 
 
Proposed Contract Period Extension:  One hundred eighty (180) day extension retroactive 9/14/2015 through 3/12/2016 
 
Total Current Contract Amount Authority:   $7,957,000.00
 
Original Approval:  6/17/2014, $7,957,000.00
 
Previous Increase(s):  N/A 
 
This Increase Requested:  N/A 
 
Estimated Fiscal Impact:  None 
 
Accounts:  Camp Accounts 25-6730, 51-6730, 52-6730, and 54-6730
 
Contract Number(s):  13-80-03-006-C
 
Concurrences:
The Chief Financial Officer and Chief Attorney have approved this item. 
 
The Vendor has met the Minority and Women Business Enterprise Ordinance Provisions.
 
District(s):  4
 
Summary:  The project is now substantially complete and the camp is open and operational, but a contract extension is now required to provide additional time for contract closeout.
 
end