Legislation Details

File #: 26-0311    Version: 1 Name:
Type: Contract Status: Approved
File created: 6/8/2026 In control: FPD Board of Commissioners
On agenda: 7/7/2026 Final action: 7/7/2026
Title: PROPOSED CONTRACT Department(s): Department of Planning and Development Vendor: Christopher B. Burke Engineering, Ltd., Rosemont, Illinois Request: Authorization for the Forest Preserves of Cook County (the "Forest Preserves") to enter into and execute Good(s) or Service(s): Phase III engineering services for construction oversight relating to construction of approximately 1.3 miles of the Des Plaines River Trail from Fullerton to North Avenue known as Segment 7. Contract Value: $1,239,837.50 (which includes 10%, $112,712.50, contingency) Contract Period: 9/1/2026 - 8/31/2029 Estimated Fiscal Impact: FY2026 $225,425.00, FY2027 $845,343.75, FY2028 $56,356.25 ($1,127,125.00) but subject to grant reimbursement of 80% ($901,700.00). The total Forest Preserves share would not exceed $338,137.50 ($225,425.00 plus an additional 10% contingency of $112,712.50). Accounts: Professional Services (51009.520830, 51010.520830, 51029.520830, 51033.520830, 51034.520830, 51036.520830, 5103...
Indexes: ADAM BIANCHI, General Superintendent
Attachments: 1. 2026.06.01 DPRT Segment 7 Location Map
Related files: 26-0310
title
PROPOSED CONTRACT

Department(s): Department of Planning and Development

Vendor: Christopher B. Burke Engineering, Ltd., Rosemont, Illinois

Request: Authorization for the Forest Preserves of Cook County (the "Forest Preserves") to enter into and execute

Good(s) or Service(s): Phase III engineering services for construction oversight relating to construction of approximately 1.3 miles of the Des Plaines River Trail from Fullerton to North Avenue known as Segment 7.

Contract Value: $1,239,837.50 (which includes 10%, $112,712.50, contingency)

Contract Period: 9/1/2026 - 8/31/2029

Estimated Fiscal Impact: FY2026 $225,425.00, FY2027 $845,343.75, FY2028 $56,356.25 ($1,127,125.00) but subject to grant reimbursement of 80% ($901,700.00). The total Forest Preserves share would not exceed $338,137.50 ($225,425.00 plus an additional 10% contingency of $112,712.50).

Accounts: Professional Services (51009.520830, 51010.520830, 51029.520830, 51033.520830, 51034.520830, 51036.520830, 51037.520830); and future Construction & Development accounts

Contract Number(s): #74000018441 issued in response to RFQ #26-80-014172

Concurrences: The Chief Financial Officer has approved this item. Final contract is subject to legal review and approval.

The contract-specific Minority- and Women-Owned Business Enterprise goal for this contract is set to zero.

District(s): 9

Summary: Phase III engineering services are needed to oversee the rehabilitation of approximately 1.3 miles of the Des Plaines River Trail, including construction of new trail alignment, elevated boardwalk structure, rehabilitation of the 1st Avenue underpass, and a trail connection to Evans Field (Elmwood Park) and to Strieby Drive (River Grove), including signalized crossing at Strieby Drive. A federal Transportation Alternatives Program (TAP-L) grant will fund up to 80% ($901,700.00) of the total contract amount of $1,127,125.00 (excluding contingency). The Forest Preserves will be responsible for 20...

Click here for full text