PROPOSED CONTRACT AMENDMENT
Department(s): Department of Planning and Development
Vendor: Matthew Paving, Inc., Oak Lawn, Illinois
Request: Authorization for the Forest Preserves of Cook County (the “Forest Preserves”) to extend and increase contract
Good(s) or Service(s): South Area Pavement, Dam and Electric Services Repairs.
Original Contract Period: 8/19/2025 - 9/18/2026
Proposed Contract Period Extension: 9/19/2026 - 9/18/2027
Total Current Contract Amount Authority: $1,939,524.55
Original Approval: 7/1/2025, $1,939,524.55
Previous Increase(s): N/A
This Increase Requested: $162,667.13
Estimated Fiscal Impact: FY2026 $162,667.13
Accounts: Land Improvements (51009.560019, 51010.560019, 51029.560019, 51033.560019, 51034.560019, 51036.560019, 51037.560019) and future Construction and Development accounts.
Contract Number(s): #74000016423 issued under Project #19-80-67G-25C2
Concurrences: The Chief Financial Officer has approved this item. Final contract amendment is subject to legal review and approval.
The vendor has met the Minority- and Women-Owned Business Enterprise Ordinance via direct participation.
District(s): 5, 11, 17
Summary: A time extension is needed due to permitting delays and a contract increase is needed to allow for unforeseen additional repair work and potential increased material cost at Midlothian Meadows, Whistler Woods and Tampier Lake dam. The current authorized contingency amount has already been largely depleted on additional work that was already completed at Dan Ryan Woods, Joe Orr Woods and Wampum Lake. The project was originally approved by the Forest Preserves of Cook County Board of Commissioners on 7/1/2025 (Board Item No. 25-0219).