File #: 24-0088    Version: 1 Name:
Type: Contract Amendment Status: Approved
File created: 12/22/2023 In control: Office of the General Superintendent
On agenda: 4/16/2024 Final action: 4/16/2024
Title: PROPOSED CONTRACT AMENDMENT Department(s): Department of Planning and Development Vendor: Pan-Oceanic Engineering Company, Inc., Chicago, Illinois Request: Authorization for the Forest Preserves of Cook County (the "Forest Preserves") to increase and extend contract Good(s) or Service(s): Paving construction services Original Contract Period: 9/8/2022 - 9/5/2023; Administrative Extension 9/5/2023 - 6/5/2024 Proposed Contract Period Extension: 6/6/2024 - 6/30/2024 Total Current Contract Amount Authority: $2,606,851.34 Original Approval: 7/26/2022, $2,606,851.34 Previous Increase(s): N/A This Increase Requested: $220,000.00 Estimated Fiscal Impact: FY 2024 $220,000.00 Accounts: Land Improvements 51009.560019, 51029.560019, 51033.560019 and 51034.560019 Contract Number(s): #74000010824 issued under Project #19-80-67G-22C4 South Area Pavement Improvements Concurrences: The Chief Financial Officer has approved this item. Final amendment is subject to legal review and app...
Indexes: EILEEN FIGEL, Interim General Superintendent
Attachments: 1. MWBE Recommendation Letter - Pan-Oceanic 24-0088
Related files: 22-0307

title

PROPOSED CONTRACT AMENDMENT

 

Department(s):  Department of Planning and Development

 

Vendor: Pan-Oceanic Engineering Company, Inc., Chicago, Illinois

 

Request: Authorization for the Forest Preserves of Cook County (the “Forest Preserves”) to increase and extend contract

 

Good(s) or Service(s): Paving construction services

 

Original Contract Period: 9/8/2022 - 9/5/2023; Administrative Extension 9/5/2023 - 6/5/2024

 

Proposed Contract Period Extension: 6/6/2024 - 6/30/2024

 

Total Current Contract Amount Authority: $2,606,851.34

 

Original Approval: 7/26/2022, $2,606,851.34

 

Previous Increase(s):  N/A

 

This Increase Requested: $220,000.00

 

Estimated Fiscal Impact: FY 2024 $220,000.00

 

Accounts: Land Improvements 51009.560019, 51029.560019, 51033.560019 and 51034.560019

 

Contract Number(s): #74000010824 issued under Project #19-80-67G-22C4 South Area Pavement Improvements

 

Concurrences: The Chief Financial Officer has approved this item. Final amendment is subject to legal review and approval. 

 

The Vendor has met the Minority- and Women-Owned Business Enterprise Ordinance via direct participation.

 

District(s): 4, 5, 6, 16, 17

 

Summary:  A contract increase and short extension is needed for additional work driven by site condition changes since the time of design and bidding. A collapsed sewer under Harlem Avenue caused severe creek erosion affecting the stability of the adjacent Tinley Creek Trail, requiring additional storm sewer, erosion control measures and landscape restoration in lieu of simple resurfacing. Additional topsoil and pavement resurfacing work were also determined necessary by the construction engineer to achieve the intended plan designs at Carlson Springs Woods, Chicago Portage Trail, Oak Forest Heritage Trail, Sauk Woods Central, and Major Taylor Trail. The project was originally approved by the Forest Preserves of Cook County Board of Commissioners on 7/26/2022 (Board Item No. 22-0307).