File #: 17-0446    Version: 1 Name: Ujamaa Construction Inc., Chicago, Illinois
Type: Contract Amendment Status: Approved
File created: 11/22/2017 In control: FPD Board of Commissioners
On agenda: 12/12/2017 Final action: 12/12/2017
Title: PROPOSED CONTRACT AMENDMENT Department(s): Planning & Development Vendor: Ujamaa Construction Inc., Chicago, Illinois Request: Authorization for the Forest Preserve District of Cook County to extend, contract Good(s) or Service(s): Construction services for Picnic Shelter Repairs at 15 locations (Busse Woods grove #26, Catherine Chevalier grove #'s 1, 2 and 3, Clayhole Woods, Country Lane Woods, Dam No. 1 Woods East #2, Dam No. 4 Woods East #2, Dan Ryan #11, Deer Grove #4, Forest Glen Woods, Lake Ave Woods East #1, Plum Creek #2, Somme Woods and Sunset Bridge Meadow) Original Contract Period: One hundred and fifty (150) days from Notice to Proceed (7/31/2017-12/28/2017) Board approved on 6/6/2017 Proposed Contract Period Extension: One hundred eighty three days (183) calendar days (12/29/2017 - 6/30/2018) Total Current Contract Amount Authority: $353,344.00 Original Approval: 6/6/2017, $353,344.00 Previous Increase(s): N/A This Increase Requested: N/A ...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent

title

PROPOSED CONTRACT AMENDMENT

 

Department(s):  Planning & Development

 

Vendor:  Ujamaa Construction Inc., Chicago, Illinois 

 

Request:  Authorization for the Forest Preserve District of Cook County to extend,  contract 

 

Good(s) or Service(s):  Construction services for Picnic Shelter Repairs at 15 locations (Busse Woods grove #26, Catherine Chevalier grove #’s 1, 2 and 3, Clayhole Woods, Country Lane Woods, Dam No. 1 Woods East #2, Dam No. 4 Woods East #2, Dan Ryan #11, Deer Grove #4, Forest Glen Woods, Lake Ave Woods East #1, Plum Creek #2, Somme Woods and Sunset Bridge Meadow)

 

Original Contract Period:  One hundred and fifty (150) days from Notice to Proceed (7/31/2017-12/28/2017) Board approved on 6/6/2017

 

Proposed Contract Period Extension:  One hundred eighty three days (183) calendar days (12/29/2017 - 6/30/2018)  

 

Total Current Contract Amount Authority:   $353,344.00

 

Original Approval:  6/6/2017, $353,344.00

 

Previous Increase(s):  N/A

 

This Increase Requested:  N/A

 

Estimated Fiscal Impact:  None

 

Accounts:  Land Improvements Accounts: 51009.560055, 51025.560055, 51026.560055, 51054.560055, 51055.560055, 51056.560055 and 51057.560055

 

Contract Number(s):  17-80-42

 

Concurrences:

The Chief Financial Officer and Chief Attorney have approved this item.

 

The Vendor has met the Minority and Women Business Enterprise Ordinance Provisions.

 

District(s):  4, 6, 9, 10, 11, 14, 15 and 17

 

Summary:  The contractor is behind schedule due to the withdrawal of a key roofing sub-contractor. Remaining work is weather dependent, requiring extension of the contract until warmer weather. 