Legislation Details

File #: 26-0263    Version: 1 Name:
Type: Contract Amendment Status: Agenda Ready
File created: 5/5/2026 In control: FPD Board of Commissioners
On agenda: 6/9/2026 Final action:
Title: PROPOSED CONTRACT AMENDMENT Department(s): Department of Planning and Development Vendor: H. W. Lochner, Inc., Chicago, Illinois Request: Authorization for the Forest Preserves of Cook County (the "Forest Preserves") to extend contract Good(s) or Service(s): Civil Engineering Services for districtwide bridge and structure inspection and design. Original Contract Period: 6/14/2022 - 6/13/2025; (Administrative Extension) 6/14/2025 - 6/13/2026 Proposed Contract Period Extension: 6/14/2026 - 6/13/2027 Total Current Contract Amount Authority: $367,840.00 Original Approval: 6/14/2022, $334,400.00 Previous Increase(s): 6/14/2025, $33,440.00 (Administrative Increase) This Increase Requested: N/A Estimated Fiscal Impact: N/A Accounts: Professional Services 51009.520830, 51033.520830, 51034.520830, 51036.520860, 51037.520830 and all future C&D accounts Contract Number(s): #74000010694 issued under Project #22-80-06 Concurrences: The Chief Financial Officer ...
Indexes: ADAM BIANCHI, General Superintendent
Related files: 26-0237, 22-0274
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

PROPOSED CONTRACT AMENDMENT

 

Department(s):  Department of Planning and Development 

 

Vendor:  H. W. Lochner, Inc., Chicago, Illinois 

 

Request: Authorization for the Forest Preserves of Cook County (the “Forest Preserves”) to extend contract 

 

Good(s) or Service(s): Civil Engineering Services for districtwide bridge and structure inspection and design. 

 

Original Contract Period: 6/14/2022 - 6/13/2025; (Administrative Extension) 6/14/2025 - 6/13/2026 

 

Proposed Contract Period Extension:  6/14/2026 - 6/13/2027 

 

Total Current Contract Amount Authority:   $367,840.00

 

Original Approval:  6/14/2022, $334,400.00

 

Previous Increase(s):  6/14/2025, $33,440.00 (Administrative Increase)

 

This Increase Requested:  N/A

 

Estimated Fiscal Impact: N/A

 

Accounts: Professional Services 51009.520830, 51033.520830, 51034.520830, 51036.520860, 51037.520830 and all future C&D accounts

 

Contract Number(s):  #74000010694 issued under Project #22-80-06

 

Concurrences: The Chief Financial Officer has approved this item. Final amendment is subject to legal review and approval.

 

The Minority- and Women-Owned Business goals are not applicable for this amendment as there is no increased fiscal impact.

 

District(s): Districtwide

 

Summary: A time extension is needed for H. W. Lochner, Inc. (“Lochner”) to assist with oversight of remaining bridge repair work at various locations including Edgebrook Golf Course. Repair work was scheduled to be completed by mid-June but started later than anticipated due to inclement weather earlier in the spring. Lochner was originally hired to inspect and design repair improvements but also provides structural expertise during construction to ensure the successful completion of the project. Repair work is expected to be completed this summer, but additional time may be needed for final inspections and closeout.

end