File #: 26-0237    Version: 1 Name:
Type: Contract Amendment Status: Agenda Ready
File created: 4/9/2026 In control: FPD Board of Commissioners
On agenda: 5/5/2026 Final action:
Title: PROPOSED CONTRACT AMENDMENT Department(s): Department of Planning and Development Vendor: MYS, Incorporated, Palos Heights, Illinois Request: Authorization for the Forest Preserves of Cook County (the "Forest Preserves") to increase and extend contract Good(s) or Service(s): Construction contract for bridge repairs at various locations across the Forest Preserves Original Contract Period: 11/7/2024 - 12/6/2025; 12/7/2025 - 6/6/2026 (Administrative Extension) Proposed Contract Period Extension: 6/7/2026 - 12/7/2026 Total Current Contract Amount Authority: $1,541,331.22 Original Approval: 9/19/2024, $1,282,358.10 Previous Increase(s): 7/1/2025, $258,973.12 This Increase Requested: $182,652.70 Estimated Fiscal Impact: FY 2026 $182,652.70 Accounts: Land Improvement 51009.560019, 51033.560019, 51034.560019, 51036.560019, 51037.560019 and future Construction and Development accounts Contract Number(s): Contract #74000014798 issued under Project #22-80-...
Indexes: ADAM BIANCHI, General Superintendent
Related files: 24-0294, 25-0255
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

PROPOSED CONTRACT AMENDMENT

 

Department(s):  Department of Planning and Development 

 

Vendor:  MYS, Incorporated, Palos Heights, Illinois 

 

Request:  Authorization for the Forest Preserves of Cook County (the “Forest Preserves”) to increase and extend contract 

 

Good(s) or Service(s):  Construction contract for bridge repairs at various locations across the Forest Preserves 

 

Original Contract Period:  11/7/2024 - 12/6/2025; 12/7/2025 - 6/6/2026 (Administrative Extension)

 

Proposed Contract Period Extension:  6/7/2026 - 12/7/2026 

 

Total Current Contract Amount Authority: $1,541,331.22

 

Original Approval:  9/19/2024, $1,282,358.10

 

Previous Increase(s):  7/1/2025, $258,973.12

 

This Increase Requested:  $182,652.70

 

Estimated Fiscal Impact:  FY 2026 $182,652.70

 

Accounts: Land Improvement 51009.560019, 51033.560019, 51034.560019, 51036.560019, 51037.560019 and future Construction and Development accounts

 

Contract Number(s):  Contract #74000014798  issued under Project #22-80-06-24C1R

 

Concurrences: The Chief Financial Officer has approved this item. Final contract amendment is subject to legal review and approval.

 

The Vendor has met the Minority- and Women-owned Business Enterprise Ordinance via direct participation.

 

District(s): Districtwide

 

Summary: A contract increase and time extension are needed due to unforeseen construction issues at a bridge located at Edgebrook Golf Course (structure ID FP #339). The construction drawings in the bid documents were based on the original design plans. During construction, the Vendor discovered existing bridge conditions that did not reflect the original design (missing anchor rods and concrete variances). This led to formal plan changes, cost increases and Construction Revision #2 being issued by the design engineer. This item was originally approved on September 19, 2024 (Board Item No. 24-0294), and the board subsequently approved a contract increase on July 1, 2025 (Board Item No. 25-0255).