Report Title: 2016 Update to the 5-Year Capital Improvement Plan
Report Period: 2016-2020
Summary: This Plan is an update of capital improvement projects and funding needs for years 2016-2020. The location of funded projects that are still in progress as well as new 2016 projects are identified on maps for northwest, north, central, southwest and south Cook County. The Plan also includes projected capital funding needs for projects in 2017-2020 that were identified by Forest Preserve staff, partner organizations and members of the public. The draft Capital Improvement Plan has been posted for additional review and comments on the Forest Preserves' website (www.fpdcc.com/cip/) during December and January and will be finalized by February 2016.
|
Indexes:
|
(Inactive) ARNOLD RANDALL, General Superintendent
|