File #: 16-0269    Version: 1 Name: Path Construction Company, Arlington Heights, Illinois
Type: Contract Amendment Status: Approved
File created: 6/7/2016 In control: FPD Board of Commissioners
On agenda: 7/12/2016 Final action: 7/12/2016
Title: PROPOSED CONTRACT AMENDMENT Department(s): Planning and Development Vendor: Path Construction Company, Arlington Heights, Illinois Request: Authorization for the Forest Preserve District of Cook County to extend a previously executed contract Good(s) or Service(s): Construction services for improvements to various buildings at the Central Garage and Warehouse Complex Original Contract Period: 10/26/2015 - 4/23/2016 and an Administrative Extension (4/24/2016 - 6/23/2016) Proposed Contract Period Extension: Two hundred seventy (270) days (6/24/2016 (retroactive) - 3/21/17) Total Current Contract Amount Authority: $1,026,100.00 Original Approval: 4/14/2015, $1,026,100.00 Previous Increase(s): N/A This Increase Requested: N/A Estimated Fiscal Impact: N/A Accounts: N/A Contract Number(s): 13-80-01-G5R2 Concurrences: The Chief Financial Officer and Chief Attorney have approved this item. The Vendor has met the Mi...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent

title

PROPOSED CONTRACT AMENDMENT

 

Department(s):  Planning and Development 

 

Vendor:  Path Construction Company, Arlington Heights, Illinois 

 

Request:  Authorization for the Forest Preserve District of Cook County to extend a previously executed  contract 

 

Good(s) or Service(s):  Construction services for improvements to various buildings at the Central Garage and Warehouse Complex 

 

Original Contract Period:  10/26/2015 - 4/23/2016 and an Administrative Extension (4/24/2016 - 6/23/2016)

 

Proposed Contract Period Extension:  Two hundred seventy (270) days

(6/24/2016 (retroactive) - 3/21/17) 

 

Total Current Contract Amount Authority:   $1,026,100.00

 

Original Approval:  4/14/2015, $1,026,100.00

 

Previous Increase(s):  N/A

 

This Increase Requested:  N/A

 

Estimated Fiscal Impact:  N/A

 

Accounts:  N/A

 

Contract Number(s):  13-80-01-G5R2

 

Concurrences:

The Chief Financial Officer and Chief Attorney have approved this item.

 

The Vendor has met the Minority and Women Business Enterprise Ordinance Provisions.

 

District(s):  1

 

Summary:  Additional time is required to perform the work.  Coordinating fire alarm systems with local fire department, bathroom and water redesign and obtaining building permits and water permit has impacted the construction period.  This project includes making improvements for ADA accessibility, life safety issues as well as office and restroom functionality. 

end