title
PROPOSED CONTRACT AMENDMENT
 
Department(s):  Planning and Development
 
Vendor:  Path Construction Co., Inc., Arlington Heights, Illinois   
 
Request:  Authorization for the Forest Preserve District of Cook County to extend  contract  
 
Good(s) or Service(s):  Repairs to Lakes and Dams
 
Original Contract Period:  5/27/2015 - 12/25/2015
 
Proposed Contract Period Extension:  Two hundred and nineteen (219) day extension 12/26/2015 - 8/1/2016 
 
Total Current Contract Amount Authority:   $467,280.00
 
Original Approval:  4/14/2015, $467,280.00
 
Previous Increase(s):  N/A
 
This Increase Requested:  N/A
 
Estimated Fiscal Impact:  None 
 
Accounts:  Trails Accounts, 25-6780, 51-6780, 52-6780, and 54-6780
 
Contract Number(s):  13-80-02-10C1-R
 
Concurrences:
The Chief Financial Officer and Chief Attorney have approved this item. 
 
The Vendor has met the Minority and Women Business Enterprise Ordinance Provisions.
 
District(s):  6, 15 and 17
 
Summary:  Work at Wampum Lake is complete and all work except landscape restoration is completed at Crabtree (Sulky Pond). Work has not yet begun at Maple Lake due to IDNR permitting delays. The permit for Maple Lake is still pending.  The project includes repairs to dams at the following lakes: Big Bend, Maple, Crabtree and Wampum. 