Skip to main content
File #: 14-0411    Version: 1 Name: Path Construction, Inc.
Type: Bid Recommendation Status: Approved
File created: 7/1/2014 In control: Finance Committee
On agenda: 9/9/2014 Final action: 9/9/2014
Title: PROPOSED BID RECOMMENDATION Presented by: ARNOLD RANDALL, General Superintendent Department: Planning & Development Request: Authorization for the Forest Preserve District of Cook County (the "Forest Preserves") to enter into a contract with Path Construction, Inc., Arlington Heights, Illinois, for building and related site improvements at the Preserves Rolling Knolls Welcome Center near Elgin. Reason: Contract 13-80-01 G7R3 Re-Bid is for the Preserve's new Rolling Knolls Welcome Center. The proposed project is to demolish a portion of the existing clubhouse that is no longer useable, remodel the remaining portion of the existing clubhouse building, build an addition to the existing clubhouse and to reconstruct the existing parking area. The proposed project includes but is not limited to the development of a meeting room with a warming kitchen, a multipurpose room, new ADA toilet facilities, a small office area to support the facility and improved site drainage for ...
Indexes: (Inactive) ARNOLD RANDALL, General Superintendent
title
PROPOSED BID RECOMMENDATION
 
Presented by: ARNOLD RANDALL, General Superintendent
 
Department:  Planning & Development
 
Request:  Authorization for the Forest Preserve District of Cook County (the "Forest Preserves") to enter into a contract with Path Construction, Inc., Arlington Heights, Illinois, for building and related site improvements at the Preserves Rolling Knolls Welcome Center near Elgin.
 
Reason:   Contract 13-80-01 G7R3 Re-Bid is for the Preserve's new Rolling Knolls Welcome Center.  The proposed project is to demolish a portion of the existing clubhouse that is no longer useable, remodel the remaining portion of the existing clubhouse building, build an addition to the existing clubhouse and to reconstruct the existing parking area. The proposed project includes but is not limited to the development of  a meeting room with a warming kitchen, a multipurpose room, new ADA toilet facilities, a small office area to support the facility and improved site drainage for the parking area and around the building. This facility also includes the use of  geothermal heating system and photovoltaic panels, both of  which are being partially funded by a grant from Illinois Clean Energy Foundation. Another contract will be let at a later date to construct additional site improvements around the property.
 
Bid Opening Date:  8/20/2014
 
Bid Results:
                                                      Recommended       
Firm                                    Base Bid            Add Alternate Bid
1.  Poulos Inc.                              $2,387,000.00            $2,513,000.00 *
2.  Path Construction Co, Inc.                  $2,397,000.00            $2,595,200.00
3.  Simpson Construction Co.                  $2,583,500.00            $2,650,800.00
4.  Cornerstone Contracting, Inc.            $2,829,000.00            $2,997,000.00
 
*The compliance administrator deemed Poulos Inc. as a non-responsive bidder for lack of MBE/WBE participation.
 
A total of six (6) alternate bid items were requested with the Bid Proposal.  The Preserves desires to include two (2) items in the scope of this contract. The bid recommendation is to award the contract with add alternates #2 & #5:  #1: Construct a landscaped dry creek, #2: Construct geo-thermal system in lieu of air cooled system, #3: Delete installation of new shade and evergreen trees, #4: Delete installation of shrubs, #5 Construct roofing system with cedar roof deck in lieu of specified system and #6: Install bollard lighting at front entry sidewalk.
 
Estimated Fiscal Impact: $2,595,200.00
 
Contract Period:  Three hundred thirty (330) days from notice to proceed
 
Account Name/Number:  Building Accounts 25-6710, 51-6710, 52-6710, 54-6710 & Grant Account 10-6710
 
District: 15
 
Concurrence(s):
The Chief Financial Officer and Chief Attorney have approved this item.